97国产成人,欧美另类在线观看,国产美女操,亚洲精品456在线播放牛牛影院,久99精品久久久,黄页视频网站,中文字幕欧美视频

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2013下半年信息系統(tǒng)項目管理師考前密卷
考試中心《2013下半年信息系統(tǒng)項目管理師考前密卷》在線考試
試卷年份2013年下半年
試題題型【單選題】
試題內(nèi)容

Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the( )
A. project management plan
B. project baseline
C. risk response plan
D. risk baseline


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容