97国产成人,欧美另类在线观看,国产美女操,亚洲精品456在线播放牛牛影院,久99精品久久久,黄页视频网站,中文字幕欧美视频

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the delivery of a key product, an issue is identified that will delay the project by two weeks. While assessing the issue, it becomes clear that team member was aware of this risk a month earlier but did not escalate it to the project manager. Who is responsible for identifying this project risk?
A、?Project risk manager.
B、?Project sponsor.
C、?Project team member.
D、?Project manager.


相關試題

推薦文章
合作網(wǎng)站內(nèi)容