PMP?每日一練試題內(nèi)容(2023/2/24)
試題1
在投標過程中,供應(yīng)商提交一份建議書,臨近截止日期時,該供應(yīng)商想作為與一家新公司首次組成的合資企業(yè)來修訂建議書。項目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:A
試題解析與討論:m.pokkc.com/st/465412484.html
試題2
一個建筑施工項目正在進行中,項目團隊正在調(diào)查施工對周邊居民的影響,并確定項目的風(fēng)險臨界值。要想保證項目正常開展,風(fēng)險臨界值應(yīng)反映在以下哪項內(nèi)容中?()查看答案
試題參考答案:C
試題解析與討論:m.pokkc.com/st/491169967.html
試題3
Management has promised you part of the incentive fee from the customer if you complete the project early. While finalizing a major deliverable,your team informs you that the deliverable meets the requirements in the contract but will not pro vide the functionality the customer needs. If the deliverable i s late, the project will not be completed early. What action should you take?查看答案
試題參考答案:B
試題解析與討論:m.pokkc.com/st/4842012580.html
試題4
項目經(jīng)理采用德爾菲技術(shù),征求兩個專家的意見,結(jié)果專家給出截然相反的結(jié)論,項目經(jīng)理收集信息并反饋給專家,項目經(jīng)理接下來怎么辦?查看答案
試題參考答案:C
試題解析與討論:m.pokkc.com/st/473559306.html
試題5
批準項目范圍之后,識別到新的需求。項目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:C
試題解析與討論:m.pokkc.com/st/472514400.html
試題6
一家公司正在開發(fā)—種軟件應(yīng)用程序,以幫助客戶執(zhí)行特定服務(wù)。在測試過程中,客戶發(fā)現(xiàn)該應(yīng)用程序存在問題。項目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:C
試題解析與討論:m.pokkc.com/st/469799287.html
試題7
A project manager would like to evaluate the various factors that influence efficiencies in a production line. Which of the following tools should be used to evaluate systematically all key factors having the most influence on the overall outcome of the project?查看答案
試題參考答案:A
試題解析與討論:m.pokkc.com/st/497109947.html
試題8
During project executing, the project manager determines that a change is needed to material purchased for the project. T he project manager calls a meeting of the team to plan how t o make the change. This is an example of:查看答案
試題參考答案:B
試題解析與討論:m.pokkc.com/st/4823016823.html
試題9
在準備工作分解結(jié)構(gòu)(WBS)時,項目經(jīng)理識別到可能存在成本超支。項經(jīng)理應(yīng)使用什么工具或技術(shù)來獲得三點估算所需的數(shù)據(jù)?查看答案
試題參考答案:A
試題解析與討論:m.pokkc.com/st/4626812338.html
試題10
項目截至目前的進度落后,經(jīng)過分析可以把原來先后順序進行的工作調(diào)整為平行進行來趕上計劃進度,這種進度壓縮技術(shù)被稱為()。查看答案
試題參考答案:C
試題解析與討論:m.pokkc.com/st/49391495.html
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |