試題1
A key deliverable is about to be sent to the customer.Team m embers complain about the time and number of tasks that need to be performed as part of the quality assurance process.T he Project manager needs the deliverable to be ready soon to obtain the first project payment. What should the project manager do to get the deliverable on time查看答案
試題參考答案:B
試題解析與討論:m.pokkc.com/st/479077737.html
試題2
項目經(jīng)理已經(jīng)制定項目預(yù)算、人員配備管理計劃和里程碑。若要開始執(zhí)行項目,項目經(jīng)理下一步應(yīng)該做什么?查看答案
試題參考答案:C
試題解析與討論:m.pokkc.com/st/4622723361.html
試題3
A marketing director and project manager meet to outline the year's marketing goals and the project they need to achieve. The director asks the project manager to ensure that the project is delivered as instructions. What should the project manager do next to obtain approval?查看答案
試題參考答案:D
試題解析與討論:m.pokkc.com/st/480683483.html
試題4
During project execution,the learn identifies several change requests that include functionality needed for project success. These failed to be included the requirements traceability matrix. To avoid this,what should the project manager do beforehand?查看答案
試題參考答案:B
試題解析與討論:m.pokkc.com/st/4783227188.html
試題5
某項目正處于規(guī)劃階段。前任項目經(jīng)理已經(jīng)完成了項目范圍說明書的編制。你剛剛受管理層的委派出任項目經(jīng)理。管理層要求你立即開始工作,并盡快完成項目計劃的編制工作。你應(yīng)該首先()。查看答案
試題參考答案:B
試題解析與討論:m.pokkc.com/st/490272250.html
試題6
項目團(tuán)隊負(fù)責(zé)制造10,000個小零件,基于集中檢查500個零件的批次質(zhì)量是控制質(zhì)量工具哪一種的實例?查看答案
試題參考答案:C
試題解析與討論:m.pokkc.com/st/475961122.html
試題7
A new project manager discovers that project B's scope and schedule of project from the previous project manager A draft..Key stakeholders don't know this is included in the range of B in the process of establishing the project. These stakeholders are assigned to project A.night months later in the project B's work.The schedule has critical activities and deliverables to next 14 months.A status meeting with all stakeholders is held in the ninth month.Assuming that this is a budget con strained project,what should the new project manager do?查看答案
試題參考答案:B
試題解析與討論:m.pokkc.com/st/48416564.html
試題8
公司正在啟動一個項目。公司的組織結(jié)構(gòu)授予項目經(jīng)理的職權(quán)比職能經(jīng)理高。這是什么組織結(jié)構(gòu)類型的實例?查看答案
試題參考答案:A
試題解析與討論:m.pokkc.com/st/4681223866.html
試題9
負(fù)責(zé)商業(yè)交易的高級經(jīng)理識別到控制交易風(fēng)險的某個系統(tǒng)需求。高級經(jīng)理起草了發(fā)放項目資金所需的商業(yè)文件,要求項目經(jīng)理立即開始項目。項目經(jīng)理首先應(yīng)該怎么做?查看答案
試題參考答案:B
試題解析與討論:m.pokkc.com/st/4824817393.html
試題10
項目經(jīng)理正在管理價值300萬美元、涉及兩個供應(yīng)商的項目,項目經(jīng)理為每名供應(yīng)商創(chuàng)建了一份工作說明書(SO W)。下列哪一項需要sow的信息?查看答案
試題參考答案:B
試題解析與討論:m.pokkc.com/st/4649322641.html
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |